Examination tickets for taking a theoretical exam in the profession “Bulldozer driver. Obtain a certificate in the specialty "stone-cutting machine operator" in Chelyabinsk Occupational safety requirements before starting work

Job Description. Management of stone-cutting operating (striping) machines with one circular saw. Production of transverse and longitudinal cuts in the extraction of standard stone and large blocks of natural stone. Installation of serviced machines on the cutting cycle. Installation and replacement of saws. Distillation of serviced machines to a new cutting cycle with a rail track. Participation in the management of a cable-cutting plant for the extraction and cutting of blocks of natural stone, installation and rearrangement in wells and trenches of its working and guide racks. Adjusting the tension of the rope-cutting installation with a tensioning device, replacing a worn-out cable with the help of a rope-laying device and mooring it. Regulation of the supply of abrasive materials to the zone of sawing stone monoliths. Identification and elimination of malfunctions in the operation of serviced machines and installations, participation in their repair.

Must know: installation of a stone-cutting operating (striping) machine with one circular saw and a cable-cutting plant for mining and cutting blocks of natural stone, running and cutting units, electric and hydraulic drives; ways to eliminate malfunctions in the operation of serviced machines and installations; technology of cutting and overturning of monoliths; characteristics of cables used on serviced machines and installations; methods for replacing and joining cables of a rope-cutting installation; physical and mechanical properties of rocks; state standards cast stone and large blocks of natural stone; rules for the use of abrasive materials.

§ 11. Machinist of a stone-cutting machine of the 5th category

Job Description. Management of stone-cutting operating (striping) machines with two circular saws or a cable-cutting installation for the extraction and cutting of natural stone blocks. Selection and provision optimal mode operation of the serviced machine (installation), its rearrangement. Production of saw cuts or drilling operations with a self-penetrating system. Rope storage and control of fixing the guide posts of a cable-cutting installation for the extraction and cutting of natural stone blocks.

Must know: design features stone-cutting machines of all types and a cable-cutting plant for the extraction and cutting of blocks of natural stone, running and cutting units, electric and hydraulic drives; technology of cutting and overturning of monoliths; the rules for choosing an abrasive according to the fractional composition and the rate of its consumption.

When operating stone-cutting operating (striping) machines with four or more circular saws in the extraction and cutting of blocks of natural stone - the 6th category.

Job Description. Management of stone-cutting operating (striping) machines with one circular saw. Production of transverse and longitudinal cuts in the extraction of standard stone and large blocks of natural stone. Installation of serviced machines on the cutting cycle. Installation and replacement of saws. Distillation of serviced machines to a new cutting cycle with the movement of the rail track. Participation in the management of a cable-cutting plant for the extraction and cutting of natural stone blocks, installation and rearrangement of its working and guide racks into wells and trenches. Adjusting the cable tension of a cable-cutting installation with a tensioner, replacing a worn-out cable with a cable-laying device and mooring it. Regulation of the supply of abrasive materials to the sawing zone of stone monoliths. Identification and elimination of malfunctions in the operation of serviced machines and installations, participation in their repair.

Must know: installation of a stone-cutting operating (striping) machine with one circular saw and a cable-cutting plant for mining and cutting blocks of natural stone, running and cutting units, electric and hydraulic drives; ways to eliminate malfunctions in the operation of serviced machines and installations; technology of cutting and overturning of monoliths; characteristics of cables used on serviced machines and installations; methods for replacing and joining cables of a rope-cutting installation; physical and mechanical properties of rocks; state standards for produced stone and large blocks of natural stone; rules for the use of abrasive materials.

§ 11. Machinist of a stone-cutting machine of the 5th category

Job Description. Management of stone-cutting operating (striping) machines with two circular saws or a cable-cutting installation for the extraction and cutting of natural stone blocks. Selection and provision of the optimal mode of operation of the serviced machine (installation), its rearrangement. Making cuts or drilling with a self-penetrating system. Reservation of cables and control of fastening of the guide posts of a cable-cutting plant for the extraction and cutting of blocks of natural stone.

Must know: design features of stone-cutting machines of all types and a cable-cutting plant for mining and cutting blocks of natural stone, running and cutting units, electric and hydraulic drives; technology of cutting and overturning of monoliths; rules for choosing an abrasive by fractional composition and its consumption rates.

When operating stone-cutting operating (striping) machines with four or more circular saws in the extraction and cutting of natural stone blocks - 6th category.

Question 1 Rules for the maintenance of mechanisms and equipment of underground lifting machines located in the chamber.

2. The actions of the driver when the machine stops as a result of the automatic activation of the safety brake due to the operation of the safety devices.

Answer 1. Maintenance of mechanisms and equipment located in the chamber of hoisting machines should be carried out in accordance with the requirements of the factory instructions for the maintenance and operation of machines and equipment used in the work.

The duties of the driver include: acceptance and delivery of the shift, control of the lifting machine during its operation, maintenance and supervision of the machine. Any malfunctions noticed are reported to the mechanic of the section, who is obliged to record in the book of acceptance and delivery of the change the causes of damage and the measures taken to eliminate the malfunctions.

The driver is obliged to: Know and comply with the safety requirements provided for by the organization of work, instructions developed at the site, workshop. To carry out in full measures to ensure safe working conditions when servicing lifting installations. Follow the requirements of the factory instructions for the maintenance and operation of machines and equipment used in the work. The drivers assigned to control the machine must be familiar with and know the electrical circuit and its operation, the hydraulic circuit and the principle of operation of its individual components.

Instruction

for the operation of the lifting machine Ts1.6 × 1.2 and Ts2 × 1.5 for lifting drivers.

Reception and delivery of shifts

Upon acceptance, an external inspection is carried out, testing of all edges and protections in the operating mode.

Subject to inspection:

  • executive body of the brake, the serviceability of the rods, the presence and tightening of locknuts on the rods and adjusting joints;
  • fastening brake liners with pads;
  • the condition of the hinged units of the brake system of the lifting machine;
  • the gap between the brake shoes and the brake rim of the drum is checked. This gap should be 0.8 mm on each side (no more than 1 mm);
  • the oil level in the oil tank and the alternate operation of the oil pumps and the pressure reducing valve are checked. The pressure of the manometer of the reducing valve should be 11-12 kg/cm 2 , the pressure of the pressure gauge on the safety valve 11-12 kg/cm 2 ; For lifting machines Ts2×1.5, the pressure of the pressure reducing valve pressure gauge should be 8-10 kg/cm 2 , the pressure of the pressure gauge on the safety valve 11-12 kg/cm 2 . The pressure on the service brake actuators must be within 8-10 kg/cm 2 .

During the bypass and inspection, the oil filter handle is turned. The pumps must be in operation alternately. The pressure on the service brake drives should be within 11-12 kg/cm 2 .

  • check the gap between the heads of the thrust bolts under the brake pads 4-5 mm;
  • on the drum of the machine, the tightening of bolt fasteners, clamps, fastening of the rope and drum, the integrity of the welds available for inspection, the laying of the rope on the drum are checked;
  • the condition of the couplings, the absence of leakage of the filling lubricant and the condition of the fingers on the finger couplings are checked;
  • checking the gearbox is reduced to checking the attachment points to the frame, the presence and level of lubrication in the crankcase at the dipstick mark, the presence of oil leakage from the gearbox. During operation, the heating of the bearings of the gearbox and the main shaft is controlled. It should not exceed 70-80 0 C.
  • checking email status. motor, the stator temperature should not exceed 55 0 С.
  • on the control panel, the ease of movement of the control handles, their fixation, the presence of marks on the depth indicator and devices for monitoring the working processes of the hydraulic system and electrical devices that are part of the equipment and the machine are checked.

When accepting and handing over a shift, the presence of protective equipment is checked: gloves, boots, a voltage indicator, the presence of posters for performing work in electrical installations, the presence of a lifting scheme, an alarm, a brake system and check logs for a leak relay, a hoist, ropes, a shift acceptance and delivery log.

Checking protections and interlocks, brakes on a stopped machine.

After external inspection, 220V voltage is applied to the control circuit for switching on the operational voltage. Then, by turning on the KRU-RN cell, we apply voltage to the reverser.

  • turn on the oil station pump on the control panel and watch the pressure gauge readings so that the oil pressure in the brake oil system is 12 atm., if necessary, switch to the backup oil pump by switching the package switch to the ShSU and the button on the control panel.
  • we check the emergency shutdown button by pressing the foot button - the KRU-RN cell should turn off
  • when the safety brake is applied, push the service brake handle “away from us” to the “disengaged” position, while the service brake should not be released.
  • check the blocking of the PT with a service brake, the zero position of the command device, the serviceability of the dynamic braking circuits, the serviceability of the VIK switches (shoe wear switch) and the Sk switches (rope loosening switch), which is located on the ladder course of the pulley. With the service brake handle partially disengaged or the command device handle in the reverse position, press the KZT button on the control panel, while the brake should not be charged.

The PT should not be charged when the VIK and VOK switches are pressed by hand (rope inlet on the pulley platform). By pressing the foot button and the button on the DT control panel, make sure that the DT current is present on the ammeter. In the absence of current, after 1-2 seconds, the FET should work.

  • the service brake must not be released when there is no voltage in the operating circuit.

Checking the car in motion.

  • Together with the signalman of the zero platform, the switches for overlifting the tub are checked. To do this, at a quiet pace (0.3-0.5 m / s), at the signal of the signalman, the tub rises up. When lifting the bucket to a height, not reaching the pile driver of 3.0 m, the PT should work. Having switched the key of the separate check of overlift by the driver and charged the TP, quietly lifts the vessel up no more than 0.5 m later, the TP should work again due to the operation of the pusher switch.

To avoid an accident, stop the overlift check when the bucket is lifted 2.3 m from the pulley platform.

  • Check the bypass switch on the control panel. Charging the TP should be possible only when the switch is turned to the right, while the reverse should turn on only in the direction of the descent of the tub down.
  • Check the setting of the electric speed limiter (EOS, ROS) according to the test instructions.
  • Perform an idle run of the bucket down, while checking the operation of the p / m on the move, the operation of the diesel engine, the operation of the service brake (the speed should be no more than 2.5 m / s.)
  • During the movement of the bucket up, the operation of the speedometer is checked.
  • 15 m before the zero site, in accordance with the mark on the UGS selsyn at the p / m, the signal for the start of deceleration should ring, and after 6 m, the red lamp on the selsyn lights up, signaling the last turn of the fine countdown arrow to the end of the ascent. During the test run, all labels are checked.

It is forbidden to transport people during the trial run.

After checking the machine, the driver slows down the machine and, if the installation is in good condition, takes duty, in case of a malfunction, the driver is obliged to call a mechanic to eliminate them. Inspection of the machine should be carried out within 15-20 minutes. The shift handover and acceptance are made out in the log signed by the drivers handing over the shift and receiving the shift.

Machine control

During operation, the driver must carefully monitor the readings of electrical measuring equipment, as well as the readings of the pressure gauge. After the start of work, the driver periodically, at least every 2 hours, checks the temperature of the bearings of the drum and gearboxes, the engine, the transformation under the brushes, sparking in starting resistors.

If the instrument readings deviate (beyond the red marks), the driver is obliged to immediately brake the machine to find out the reasons for the deviation and take measures to eliminate them. It is also necessary to carefully monitor the indications of the arrows of the depth indicator. If during the movement of the bucket the arrow stops or moves in jerks, the machine must be braked and the cause found out. When the bucket approaches the horizon or zero ground, the driver must begin to slow down to 0.8 m / s and be ready to stop the machine, increase monitoring of the marks on the selsyn, ammeter, tachometer.

For 5 m before the indicated marks, the speed should be no more than 1.0 m / s, the driver must carefully listen to the movement of the machine, observe the winding of the rope on the drum and its condition. The uneven running of the machine, abnormal sounds in its mechanisms, rope jerks, the presence of smoke and burning indicate a violation in the operation of the lift. The car must be stopped immediately.

Do not operate the machine in the event of a malfunction:

  • brake system
  • Protection circuit equipment
  • lifting rope
  • Tow hitch
  • pile pulleys
  • When any objects get under the rope.

If these violations occur during the run, the machine must be stopped and braked with a safety brake, subsequent switching on can only be done after the faults have been eliminated.


Ministry of Education, Science Youth Policy
Trans-Baikal Territory
GOU NPO " Professional institute No. 30"
EXAM TICKETS
to take a theoretical exam
by profession "BULLDOZER ENGINEER"
Kokuy 2014
I approve
Chief State
engineer-inspector of state technical supervision for Sretensky district
Gilev A.G.
_________________
(__)_________(______)
Parshin I.S.
Examination tickets for taking a theoretical exam in the profession "Bulldozer driver" For students by profession 13583 "Bulldozer driver" - GOU NPO PU No. 30, 2014. - 25s.
Considered and recommended for use at a meeting of the methodological commission (Minutes No. dated).
Examination tickets for taking a theoretical exam in the profession "Bulldozer driver" for students in the profession 13583 "Bulldozer driver". Studying the basic mechanisms of the base machines of bulldozers and bulldozers-rippers, the technology of excavation by bulldozers, as well as the basics technical operation and occupational safety when working on machines.
Compiled by: teacher of the first qualification category GOU NPO PU No. 30 - Parshin Ivan Sergeevich
Introduction.
Materials for testing knowledge are used when taking a theoretical exam in the profession 13583 "Bulldozer driver".
Each ticket consists of 8 tasks that contain questions on the device, operation, earthmoving operations with bulldozers and bulldozers-rippers installed on base machines.
Persons who have reached the age of 18 and have undergone special training are allowed to take the exams.
Ticket number 1
1. Self-propelled earthmoving machine designed for the development and movement of soil, rocks, building and other materials.
1) grader
2)excavator
3) bulldozer
2. What are the main parts of a bulldozer?
1) Engine, chassis, equipment.
2) Base machine, attachment
3) Bulldozer, ripper and blade.
3. The sequence of interaction of mechanisms that ensure the movement of the bulldozer is ...
1) transmission
2) chassis
3) kinematic diagram
4. Depending on the type of dumps, bulldozers are distinguished?
1) with fixed blade,
2) with swivel blade,
3) with a universal blade.
4) All of the above.
5. At what age are persons allowed to drive a bulldozer?
1) from 17
2) from 18
3) from 20
6. The planetary gearbox of the T-10M tractor consists of:
1) of five planetary gears and five clutches
2) of four planetary gears and the same number of clutches
3) of three planetary gears and three clutches
7. The material for the construction of the subgrade is:
1) rock
2) sand
3) soil
8. Under which number is the push bar?
1) 9
2) 8
3) 6

Ticket number 2
1. How are bulldozers classified by purpose?
1) general purpose
2) special
3) universal
4) correct answers 1, 2
5) all of the above.
2. How is the fixed blade installed on the bulldozer relative to its main axis?
1) diagonally to the axis.
2) perpendicular to the axis.
3) at an adjustable angle to the axis.
3. How many disc clutches can be installed on basic tractors?
1) single disc
2) double disc
3) multi-disk
4) all of the above
5) correct answer 1 and 2
4. The support roller of the cantilever type has a pair of internal ……. holding the upper branch of the sideshift track (insert missing word).
1) cuff
2) rings
3) rebord.
5. The ratio of the number of teeth of the driven gear and the drive gear is called the ratio
1) gear
2) leading
3) slave.
6. What kind of suspension is available for utility rippers?
1) three-link
2) four-link
3) Answer 1 and 2
4) all of the above.
7. Engineering soil structure, which serves as the basis for highway or rail track railway This
1) subgrade
2) right of way
3) both listed
8. Under what number is the thrust indicated?
1) 2
2) 5
3) 3

Ticket number 3
1. Caterpillar chains according to the type of hinged joints are distinguished:
1) with closed hinge
2) with open hinge
3) with open and closed hinge.
2. Flat areas of the terrain that do not require either excavation or embankment are called?
1) linear
2) zero
3) planning.
3.What is the base machine use?
1) caterpillar tractor
2) wheeled tractor
3) tractor
4) any of the above.
4. What is the lower edge of the blade equipped with?
1) teeth
2) blade
3) knives
5. What is used to deepen and raise the ripper?
1) rope
2) hydraulic cylinder
3) mechanically
6. Rotary blade can be installed:
1) perpendicular to the tractor axis
2) diagonally to the tractor axis
3) by any of the listed methods.
7. Due to what are the clutch discs in a compressed state?
1) due to hydraulics
2) due to pressure springs
3) due to oil flow
8. Under what number is the spherical blade?
1) 4
2) 5
3) 6
4) all of the above

Ticket number 4
What value should not exceed the rises of the slopes along which the soil is supplied when cultivating embankments with transverse passages from the reserve?
40%
35%
30%
25%
Which bulldozers are economically viable for layer mining and moving materials over long distances?
Heavy
Lungs
Medium
Superheavy
Bulldozers carry out layer-by-layer development and movement of materials at a distance of ……..?
100-200 meters.
50 - 150 meters.
200-250 meters.
200-300 meters.
Is the embankment erected by bulldozers?
Longitudinal one-way movements of the machine.
Both answers are correct
Are excavations being developed?
All answers are correct

Transverse moves.
Do they cut canals, irrigation facilities, trenches and pits?
Transverse passages of the bulldozer with a gradual displacement of the machine along the structures.
Cross passages from the reserve.
Longitudinal double-sided passages
What schemes of movement of bulldozers are used when loosening rocks and permafrost soils?
Longitudinally - annular and spiral
Shuttle and longitudinal - transverse
All listed.
What makes a bulldozer run smoothly?
one). frames
2) Shock absorbers.
3) Springs.
4) Pendants.

Ticket number 5
What method is used for a small length of recesses?
Cross passages from the reserve.
Longitudinal two-way passage
Cross passage.
Longitudinal one-way movement of the machine.
What is the most efficient and safe method for punching terraces on a slope?
Cross passages of the machine on a slope.
Longitudinal passes with a moldboard installed with a bias.
Direct machine passes.
What type of maintenance is performed after a certain amount of time the machine has been used?
Complete
Every shift
seasonal
Planned
On a horizontal surface, the blade is sharply buried in the ground to the full depth, determined by ...? Engine loading
Movement speeds.
Tractor skid
The formation of a prism in front of the blade.
If the depth of freezing of rocks is more than 70 cm, then it is necessary to loosen ....... tooth (teeth) in two or three passes with a loosening depth of 30 ... 40 cm?
One
two
Three
Correct answers 1.3.
Development of a bottomhole with constant small chips allows …..?
reduce soil resistance during working passes
increase movement speed.
Lengthen prism set path
Correct answers 1 and 2
Correct answers 2 and 3
All right
The length of the dragging prism set is?
6-10 meters
5-15 meters
10-20 meters
20-30 meters
What scheme of work is used when it is necessary to obtain a smaller breed?
Spiral
Shuttle with mixing
Longitudinal - transverse
Longitudinally - annular
Ticket number 6
What type of transmission does the DET-250, DET-330 tractor have?
Mechanical
Hydromechanical
Electromechanical
Hydrostatic.
What should be the distance between the trenches when extracting channels?
0.8-0.9 meters.
0.2-0.5 meters.
0.4-0.6 meters.
0.5-0.7 meters.
Bulldozers-rippers destroy rock and frozen rocks under the influence of ....... and tearing with a tip and a rack?
Tractor weights.
Tooth compression
Blade pressure on the ground
All listed.
When working on ....... the traction force of the machine is reduced by 35 ... 45% due to a decrease in the adhesion of the undercarriage to the ground?
Sandy soilsRocksFrozen soilsCorrect answers 2.3.
What can be used to partially improve the adhesion of tractor tracks to the ground?
Special overlays for tracks.
Ballast installation
Installation of new or restored tracks.
With a depth of freezing of rocks by 50 ... 70 cm, can an array be loosened ... with teeth (tooth)?
One
two
Three
Correct answers 1.3.
What type of transmission does the tractor T-25.01, T-500 have?
Mechanical
Hydromechanical
Electromechanical
Hydrostatic.
What determines the choice of loosening scheme?
From the permeability of soils.
From the strength and nature of soils.*
From water absorption of soils
Correct answers 2.3
All of the above are correct answers.
Ticket number 7
What method of development and mining is used to match the performance of loading facilities?
Trench with loading into a dump truck by a loader At an angle with loading from a pile into a dump truck by an excavator.
Open with pre-loosening
Two bulldozers and a loader.
When developing an array in a trench way, a bulldozer-ripper loosens the rock in layers at the bottom of the trench. Then, with the blade, with the ripper raised, the rock is moved to the pile .......? Shuttle movements of the machine.
Spiral Machine
Longitudinally - transverse movements of the machine.
Longitudinally - circular movements of the machine.
With the paired operation of two or three bulldozers, the spillage of soil into the side rollers between the machines is limited, and this contributes to .......?
Reducing the mass of the soil being moved, since soil spillage into the side rollers between the machines is not limited.
Both options are correct.
If necessary, leave the car need to ...?
Apply the parking brake and turn off the engine.
Place the transmission lever in first gear.
Turn on alarms.
What allows you to do the development of a face with constant small chips?
Increase soil resistance on working passes
Increase movement speed.
Increase traction force.
Reduce soil resistance on working passes
Correct answers 2.4
All of the above answers are correct
What type of transmission does the T-170 tractor have?
Mechanical
Hydromechanical
Electromechanical
Hydrostatic.
When working downhill under the action of the mass of the bulldozer increases ...? The speed of the tractor.
Traction force*

To fix the position of the blade skew in the hydraulic lines of the hydraulic cylinders controlling it, it is provided ... ..?
Stop valve.
Hydraulic lock.*
bypass valve.
Ticket number 8
What type of transmission do Caterpillar bulldozers have?
Mechanical
Hydromechanical
Electromechanical
Hydrostatic.
A wheel fixed motionless on the torque converter housing is called?
pump wheel
Turbine wheel.
Reactor.
What division is installed in the hydraulic system of the DZ-171.03 bulldozer?
10MPa
16MPa
20MPa
When loosening soils of category IV and strong rocks, it is advisable to organize the operation of machines according to ... ... schemes, since they provide the highest productivity?
Longitudinally - annular and spiral
Shuttle and longitudinal - transverse
All listed.
What are rigid screw braces used for?
For setting the blade cutting angle.
To set the skew.
Both options are correct.
Which of the proposed options affects the performance and productivity of machines?
Bulldozer knives.
Ripper tip.
Quality of car maintenance.
The speed of the car.
Completeness of filling of the drawing prism.
All of the above
On what grounds are rippers classified?
By purpose and traction
By design and location
By putting them into action
In an electric transmission, torque is transmitted from the engine to ……?
Clutch
Gearboxes
Power generator
Electric motor
Ticket number 9
What is the reason for the slippage of the brake of the planetary mechanism of the caterpillar machine?
Small clearance in bearings
Worn brake pads.
Large clearance in bearings.
The basis of the bulldozer hydraulic control system is?
Oil pump.
Hydraulic tank.
Pipelines and hoses.
Is the plow blade made of wear-resistant materials to increase wear resistance?
Yes.
No, because these are expensive materials.
No.
What type of maintenance is included in TO No. 1?
EO.
TO №2.
CO.
TR and CR.
All correct answers
Is it possible to immediately bury the bulldozer blade to a greater depth?
Can
It is forbidden.
You can't, as the engine may stall.
The tension of the caterpillar on the tractor T-11.01 is carried out using?
Screw tensioner with shock-absorbing device.
Hydraulic tensioner.
Lubricated tension mechanism.
Which of the following is a source of electrical energy?
Electric starter
Accumulator battery.
Generator
Magneto.
All except 1.
When working on bulk soils, the cutting angle of the blade should be?
60-650
65-700
70-850
Ticket number 10
When transversely moving soil from a reserve, is it advisable to use ...... a method of developing materials?
Trench.
Spiral.
Shuttle
Is it used to automatically maintain the generator voltage within the specified limits?
Protection relay.
Relay-regulator.
Contactors.
Switches
A permanently closed dry friction clutch is called?
final drive
Main gear.
Side clutch.
What is the torque of the diesel converted in the torque converter transferred to?
pump wheel
Turbine shaft.
Reactor.
Gearboxes.
When mining open way apply ... .. a detachment of machines, which includes 3-5 bulldozers, rippers, an excavator or loader and several dump trucks?
Mixed.
Complex.
Cyclic.
inline
When working on wet soils, the cutting angle of the blade should be?
30-450
45-500
50-650
An earthen structure erected by dumping soil on the surface of the earth is called?
In bulk.
sawn-off
Backfill.
trench.
Do they contribute to the increase in the drawing prism?
Extenders
Extensions.
Openers mounted on the sides of the blade.
All of the above.
ANSWER TABLE
Ticket number Question numbers
1 2 3 4 5 6 7 8
1 3 2 3 4 2 1 3 6
2 4 2 5 3 1 3 3 2
3 3 2 4 3 2 3 2 4
4 3 1 2 3 1 1 4 4
5 2 1 4 1 1 4 1 3
6 3 3 2 3 1 3 2 3
7 4 1 1 1 5 1 2 2
8 4 3 2 1 3 6 1 3
9 2 1 1 1 1 3 5 1
10 1 2 3 2 1 2 1 4
List of recommended literature.
G.I. Gladov A.M. Petrenko "Tractors. Device and maintenance» Tutorial for primary vocational education. Publishing Center "Academy". 2008
Rodichev V.A. "Tractors" Textbook for institutions of primary vocational education. Publishing Center "Academy" IRPO publishing house "Kolos". 2008
Ulman I. E., Ignatiev G.S., Borisenko V.A. and etc. Maintenance and repair of machines. - M .: Agropromizdat, 1990.
Puchin E.A. Kushnarev L.I. Petrishchev N.A. edited by E.A. Abyss. Maintenance and repair of tractors: textbook early. prof. education 4th edition ster. - M .: Publishing center "Academy", 2008-208s
Babusenko S.M. Repair of tractors and cars. -3rd ed., revised. and additional M.: Agropromizdat, 1999.-351s.
Itinskaya N.I., Kuznetsov N.A. Automotive operating materials. - 3rd ed., revised. and additional – M.: Agropromizdat, 1987.-271p.
Rodinson E.G., Polosin M.D. Bulldozer driver. Tutorial. - M. Ed. Center "Academy", 2007, -67s
Content.
Introduction………………………………………………………………….3
Ticket No. 1…………………………………………………………………….4
Ticket number 2…………………………………………………………………….5
Ticket No. 3…………………………………………………………………….6
Ticket No. 4…………………………………………………………………….7
Ticket No. 5…………………………………………………………………….8
Ticket No. 6…………………………………………………………………….9
Ticket number 7…………………………………………………………………….10
Ticket No. 8…………………………………………………………………….11
Ticket number 9………………………………………………………………….12
Ticket No. 10………………………………………………………………..13
Answer table ……………………………………………………………………………………14
List of recommended literature……………...………….………….15
Contents …………………………………………………………………16